| |








S
S-Curve
Graphic display of cumulative costs,
labor hours, or other quantities, plotted against time. The name
derives from the S-like shape of the curve (flatter at the beginning
and end, steeper in the middle) produced on a project that starts
slowly, accelerates, and then tails off.
Schedule
See project schedule.
Schedule Analysis
See network analysis.
Schedule Compression
See duration compression.
Schedule Control
Controlling changes to the project schedule.
Schedule Development
Analyzing activity sequences, activity
durations, and resource requirements to create the project schedule.
Schedule Performance Index
(SPI) The ratio of work performed to
work scheduled (BCWP/BCWS). See earned value.
Schedule Variance
(SV) (1) Any difference between the scheduled
completion of an activity and the actual completion of that activity.
(2) In earned value, BCWP less BCWS.
Scheduled Finish Date
(SF) The point in time work was scheduled
to finish on an activity. The scheduled finish date is normally
within the range of dates delimited by the early finish date and
the late finish date.
Scheduled Start Date
(ISS) The point in time work was scheduled
to start on an activity. The scheduled start date is normally within
the range of dates delimited by the early start date and the late
start date.
Scope
The sum of the products and services
to be provided as a project.
Scope Baseline
See baseline.
Scope Change
Any change to the project scope. A scope
change almost always requires an adjustment to the project cost
or schedule.
Scope Change Control
Controlling changes to project scope.
Scope Definition
Decomposing the major deliverables into
smaller, more manageable components to provide better control.
Scope Planning
Developing a written scope statement
that includes the project justification, the major deliverables,
and the project objectives.
Scope Verification
Ensuring that all identified project
deliverables have been completed satisfactorily.
Should-Cost Estimates
An estimate of the cost of a product
or service used to provide an assessment of the reasonableness of
a prospective contractor's proposed cost.
Slack
Term used in PERT for float.
Solicitation
Obtaining quotations, bids, offers, or
proposals as appropriate.
Solicitation Planning
Documenting product requirements and
identifying potential sources.
Source Selection
Choosing from among potential contractors.
Staff Acquisition
Getting the human resources needed assigned
to and working on the project.
Stakeholder
Individuals and organizations who are
involved in or may be affected by project activities.
Start Date
A point in time associated with an activity's
start, usually qualified by one of the following: actual, planned,
estimated, scheduled, early, late, target, baseline, or current.
Start-to-Finish
See logical relationship.
Start-to-Start
See logical relationship.
Statement of Work
(SOW) A narrative description of products
or services to be supplied under contract.
Subnet
A subdivision of a project network diagram
usually representing some form of subproject.
Subnetwork
See subnet.
Successor Activity
(1) In the arrow diagramming method,
the activity which departs a node. (2) In the precedence diagramming
method, the ''to'' activity.
©2001, Strategic Management Group, Inc.
All
Rights Reserved
|