Project Leadership Continuous Learning and Education Online
Home Page
Introduction
Preparatory Work
Post-Work
Follow-Up
The Communicator
Site Map
Preparatory Work
Glossary
 

a b c d-e f g-i j-l m-n o-p q-r s t-z


S

S-Curve

Graphic display of cumulative costs, labor hours, or other quantities, plotted against time. The name derives from the S-like shape of the curve (flatter at the beginning and end, steeper in the middle) produced on a project that starts slowly, accelerates, and then tails off.
Schedule
See project schedule.
Schedule Analysis
See network analysis.
Schedule Compression
See duration compression.
Schedule Control
Controlling changes to the project schedule.
Schedule Development
Analyzing activity sequences, activity durations, and resource requirements to create the project schedule.
Schedule Performance Index
(SPI) The ratio of work performed to work scheduled (BCWP/BCWS). See earned value.
Schedule Variance
(SV) (1) Any difference between the scheduled completion of an activity and the actual completion of that activity. (2) In earned value, BCWP less BCWS.
Scheduled Finish Date
(SF) The point in time work was scheduled to finish on an activity. The scheduled finish date is normally within the range of dates delimited by the early finish date and the late finish date.
Scheduled Start Date
(ISS) The point in time work was scheduled to start on an activity. The scheduled start date is normally within the range of dates delimited by the early start date and the late start date.
Scope
The sum of the products and services to be provided as a project.
Scope Baseline
See baseline.
Scope Change
Any change to the project scope. A scope change almost always requires an adjustment to the project cost or schedule.
Scope Change Control
Controlling changes to project scope.
Scope Definition
Decomposing the major deliverables into smaller, more manageable components to provide better control.
Scope Planning
Developing a written scope statement that includes the project justification, the major deliverables, and the project objectives.
Scope Verification
Ensuring that all identified project deliverables have been completed satisfactorily.
Should-Cost Estimates
An estimate of the cost of a product or service used to provide an assessment of the reasonableness of a prospective contractor's proposed cost.
Slack
Term used in PERT for float.
Solicitation
Obtaining quotations, bids, offers, or proposals as appropriate.
Solicitation Planning
Documenting product requirements and identifying potential sources.
Source Selection
Choosing from among potential contractors.
Staff Acquisition
Getting the human resources needed assigned to and working on the project.
Stakeholder
Individuals and organizations who are involved in or may be affected by project activities.
Start Date
A point in time associated with an activity's start, usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, target, baseline, or current.
Start-to-Finish
See logical relationship.
Start-to-Start
See logical relationship.
Statement of Work
(SOW) A narrative description of products or services to be supplied under contract.
Subnet
A subdivision of a project network diagram usually representing some form of subproject.
Subnetwork
See subnet.
Successor Activity
(1) In the arrow diagramming method, the activity which departs a node. (2) In the precedence diagramming method, the ''to'' activity.



Back to Search


©2001, Strategic Management Group, Inc.

All Rights Reserved