Project Leadership Continuous Learning and Education Online
Home Page
Introduction
Preparatory Work
Post-Work
Follow-Up
The Communicator
Site Map
Preparatory Work
Glossary
 

a b c d-e f g-i j-l m-n o-p q-r s t-z


J

No terms for J


K

Key Event Schedule

See master schedule.


L

Lag

A modification of a logical relationship which directs a delay in the successor task. For example, in a finish-to-start dependency with a 10-day lag, the successor activity cannot start until 10 days after the predecessor has finished. See also lead.
Late Finish Date
(LF) In the critical path method, the latest possible point in time that an activity may be completed without delaying a specified milestone (usually the project finish date).
Late Start Date
(LS) In the critical path method, the latest possible point in time that an activity may begin without delaying a specified milestone (usually the project finish date).
Lead
A modification of a logical relationship which allows an acceleration of the successor task. For example, in a finish-to-start dependency with a 10-day lead, the successor activity can start 10 days before the predecessor has finished. See also lag.
Level of Effort
(LOE) Support-type activity (e.g., vendor or customer liaison) that does not readily lend itself to measurement of discrete accomplishment. It is generally characterized by a uniform rate of activity over a specific period of time.
Leveling
See resource leveling.
Life-cycle Costing
The concept of including acquisition, operating, and disposal costs when evaluating various alternatives.
Line Manager
(1) The manager of any group that actually makes a product or performs a service. (2) A functional manager.
Link
See logical relationship.
Logic
See network logic.
Logic Diagram
See project network diagram.
Logical Relationship
A dependency between two project activities, or between a project activity and a milestone. See also precedence relationship. The four possible types of logical relationships are: Finish-to-start: the ''from'' activity must finish before the ''to'' activity can start; Finish-to-finish: the ''from'' activity must finish before the ''to'' activity can finish; Start-to-start: the ''from'' activity must start before the ''to'' activity can start; Start-to-finish: the ''from'' activity must start before the ''to'' activity can finish.
Loop
A network path that passes the same node twice. Loops cannot be analyzed using traditional network analysis techniques such as CPM and PERT. Loops are allowed in GERT.



Back to Search


©2001, Strategic Management Group, Inc.

All Rights Reserved