Project Leadership Continuous Learning and Education Online
Home Page
Introduction
Preparatory Work
Post-Work
Follow-Up
The Communicator
Site Map
Preparatory Work
Glossary
 

a b c d-e f g-i j-l m-n o-p q-r s t-z


D

Data Date

(DD) The point in time that separates actual (historical) data from future (scheduled) data. Also called as-of date.
Definitive Estimate
See estimate.
Deliverable
Any measurable, tangible, verifiable outcome, result, or item that must be produced to complete a project or part of a project. Often used more narrowly in reference to an external deliverable, which is a deliverable that is subject to approval by the project sponsor or customer.
Dependency
See logical relationship.
Dummy Activity
An activity of zero duration used to show a logical relationship in the arrow diagramming method. Dummy activities are used when logical relationships cannot be completely or correctly described with regular activity arrows. Dummies are shown graphically as a dashed line headed by an arrow.
Duration
(DU) The number of work periods (not including holidays or other non-working periods) required to complete an activity or other project element. Usually expressed as workdays or workweeks. Sometimes incorrectly equated with elapsed time. See also effort.
Duration Compression
Shortening the project schedule without reducing the project scope. Duration compression is not always possible and often requires an increase in project cost.


E

Early Finish Date

(EF) In the critical path method, the earliest possible point in time on which the uncompleted portions of an activity (or the project) can finish based on the network logic and any schedule constraints. Early finish dates can change as the project progresses and changes are made to the project plan.
Early Start Date
(ES) In the critical path method, the earliest possible point in time on which the uncompleted portions of an activity (or the project) can start, based on the network logic and any schedule constraints. Early start dates can change as the project progresses and changes are made to the project plan.
Earned Value
(EV) (1) A method for measuring project performance. It compares the amount of work that was planned with what was actually accomplished to determine if cost and schedule performance is as planned. See also actual cost of work performed, budgeted cost of work scheduled, budgeted cost of work performed, cost variance, cost performance index, schedule variance, and schedule performance index. (2) The budgeted cost of work performed for an activity or group of activities.
Earned Value Analysis
See definition (1) under earned value.
Effort
The number of labor units required to complete an activity or other project element. Usually expressed as staffhours, staffdays, or staffweeks. Should not be confused with duration.
Estimate
An assessment of the likely quantitative result. Usually applied to project costs and durations and should always include some indication of accuracy (e.g., + x percent). Usually used with a modifier (e.g., preliminary, conceptual, feasibility). Some application areas have specific modifiers that imply particular accuracy ranges (e.g., order-of-magnitude estimate, budget estimate, and definitive estimate in engineering and construction projects).
Estimate At Completion
(EAC) The expected total cost of an activity, a group of activities, or of the project when the defined scope of work has been completed. Most techniques for forecasting EAC include some adjustment of the original cost estimate based on project performance to date. Also shown as ''estimated at completion.'' Often shown as EAC = Actuals-to-date + ETC. See also earned value and estimate to complete.
Estimate To Complete
(ETC) The expected additional cost needed to complete an activity, a group of activities, or the project. Most techniques for forecasting ETC include some adjustment to the original estimate based on project performance to date. Also called ''estimated to complete.'' See also earned value and estimate at completion.
Event-on-Node
A network diagramming technique in which events are represented by boxes (or nodes) connected by arrows to show the sequence in which the events are to occur. Used in the original Program Evaluation and Review Technique.
Exception Report
Document that includes only major variations from plan (rather than all variations).
Expected Monetary Value
The product of an event's probability of occurrence and the gain or loss that will result. For example, if there is a 50 percent probability that it will rain, and rain will result in a $100 loss, the expected monetary value of the rain event is $50 (.5 x $100).



Back to Search


©2001, Strategic Management Group, Inc.

All Rights Reserved