Project Leadership Continuous Learning and Education Online
Home Page
Introduction
Preparatory Work
Post-Work
Follow-Up
The Communicator
Site Map
Preparatory Work
Glossary
 

a b c d-e f g-i j-l m-n o-p q-r s t-z


C

Calendar Unit

The smallest unit of time used in scheduling the project. Calendar units are generally in hours, days, or weeks, but can also be in shifts or even in minutes. Used primarily in relation to project management software.
Change Control Board
(CCB) A formally constituted group of stakeholders responsible for approving or rejecting changes to the project baselines.
Change in Scope
See scope change.
Chart of Accounts
Any numbering system used to monitor project costs by category (e.g., labor, supplies, materials). The project chart of accounts is usually based upon the corporate chart of accounts of the primary performing organization. See also code of accounts.
Charter
See project charter.
Code of Accounts
Any numbering system used to uniquely identify each element of the work breakdown structure. See also chart of accounts.
Communications Planning
Determining the information and communications needs of the project stakeholders.
Concurrent Engineering
An approach to project staffing that, in its most general form, calls for implementers to be involved in the design phase. Sometimes confused with fast tracking.
Contingencies
See reserve and contingency planning.
Contingency Allowance
See reserve.
Contingency Planning
The development of a management plan that identifies alternative strategies to be used to ensure project success if specified risk events occur.
Contingency Reserve
A separately planned quantity used to allow for future situations which may be planned for only in part (sometimes called ''known unknowns''). For example, rework is certain, the amount of rework is not. Contingency reserves may involve cost, schedule, or both. Contingency reserves are intended to reduce the impact of missing cost or schedule objectives. Contingency reserves are normally included in the project's cost and schedule baselines.
Contract
A contract is a mutually binding agreement which obligates the seller to provide the specified product and obligates the buyer to pay for it. Contracts generally fall into one of three broad categories: Fixed price or lump sum contracts, Cost reimbursable contracts, or Unit price contracts.
Contract Administration
Managing the relationship with the seller.
Contract Close-out
Completion and settlement of the contract, including resolution of all outstanding items.
Control
The process of comparing actual performance with planned performance, analyzing variances, evaluating possible alternatives, and taking appropriate corrective action as needed.
Control Charts
Control charts are a graphic display of the results, over time and against established control limits, of a process. They are used to determine if the process is ''in control'' or in need of adjustment.
Corrective Action
Changes made to bring expected future performance of the project into line with the plan.
Cost Budgeting
Allocating the cost estimates to individual project components.
Cost Control
Controlling changes to the project budget.
Cost Estimating
Estimating the cost of the resources needed to complete project activities.
Cost of Quality
The costs incurred to ensure quality. The cost of quality includes quality planning, quality control, quality assurance, and rework.
Cost Performance Index
(CPI) The ratio of budgeted costs to actual costs (BCWP/ACWP). CPI is often used to predict the magnitude of a possible cost overrun using the following formula: original cost estimate/CPI = projected cost at completion. See also earned value.
Cost Plus Fixed Fee Contract
(CPFF) A type of contract where the buyer reimburses the seller for the seller's allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).
Cost Plus Incentive Fee Contract
(CPIF) A type of contract where the buyer reimburses the seller for the seller's allowable costs (allowable costs are defined by the contract), and the seller earns its profit if it meets defined performance criteria.
Cost Variance
(CV) (1) Any difference between the estimated cost of an activity and the actual cost of that activity. (2) In earned value, BCWP less ACWP.
Crashing
Taking action to decrease the total project duration after analyzing a number of alternatives to determine how to get the maximum duration compression for the least cost.
Critical Activity
Any activity on a critical path. Most commonly determined by using the critical path method. Although some activities are ''critical'' in the dictionary sense without being on the critical path, this meaning is seldom used in the project context.
Critical Path
In a project network diagram, the series of activities which determines the earliest completion of the project. The critical path will generally change from time to time as activities are completed ahead of or behind schedule. Although normally calculated for the entire project, the critical path can also be determined for a milestone or subproject. The critical path is usually defined as those activities with float less than or equal to a specified value, often zero. See also critical path method.
Critical Path Method
(CPM) A network analysis technique used to predict project duration by analyzing which sequence of activities (which path) has the least amount of scheduling flexibility (the least amount of float). Early dates are calculated by means of a forward pass using a specified start date. Late dates are calculated by means of a backward pass starting from a specified completion date (usually the forward pass's calculated project early finish date).
Current Finish Date
The current estimate of the point in time when an activity will be completed.
Current Start Date
The current estimate of the point in time when an activity will begin.



Back to Search


©2001, Strategic Management Group, Inc.

All Rights Reserved