| |








A
Accountability Matrix
See responsibility
assignment matrix.
Activity
An element of work performed during the
course of a project. An activity normally has an expected duration,
an expected cost, and expected resource requirements. Activities
are often subdivided into tasks.
Activity Definition
Identifying the specific activities that
must be performed in order to produce the various project deliverables.
Activity Description
(AD) A short phrase or label used in
a project network diagram. The activity description normally describes
the scope of work of the activity.
Activity Duration Estimating
Estimating the number of work periods
which will be needed to complete individual activities.
Activity-On-Arrow
(AOA) See arrow diagramming
method.
Activity-On-Node
(AON) See precedence
diagramming method.
Actual Cost of Work Performed
(ACWP) Total costs incurred (direct and
indirect) in accomplishing work during a given time period. See
also earned value.
Actual Finish Date
(AF) The point in time that work actually
ended on an activity. (Note: in some application areas, the activity
is considered ''finished'' when work is ''substantially complete.'')
Actual Start Date
(AS) The point in time that work actually
started on an activity.
Administrative Closure
Generating, gathering, and disseminating
information to formalize project completion.
Application Area
A category of projects that have common
elements not present in all projects. Application areas are usually
defined in terms of either the product of the project (i.e., by
similar technologies or industry sectors) or the type of customer
(e.g., internal vs. external, government vs. commercial). Application
areas often overlap.
Arrow
The graphic presentation of an activity.
See also arrow diagramming method.
Arrow Diagramming Method
(ADM) A network diagramming technique
in which activities are represented by arrows. The tail of the arrow
represents the start and the head represents the finish of the activity
(the length of the arrow does not represent the expected duration
of the activity). Activities are connected at points called nodes
(usually drawn as small circles) to illustrate the sequence in which
the activities are expected to be performed. See also precedence
diagramming method.
AS
Actual Start date.
As-of Date
See data date.
©2001, Strategic Management Group, Inc.
All
Rights Reserved
|